Objectives
- Generation and collection of baseline data for various environmental components.
- Identification and quantification of significant environmental impacts due to the project and associated activities.
- Evaluation of impacts due to proposed activities and preparation of an environmental impact statement along with mitigation measures.
- Preparation of appropriate Environmental Management Plan (EMP) to minimizing adverse impacts.
- Detailed study carried out for Sea & Road Traffic / Oil Contingency Plan / Cargo Handling Facilities at Port.
- Post project Environmental Monitoring Program.
- Preparation of Risk Assessment and Disaster Management Plan.
Funded by
- GujaratMaritime Board, Gandhinagar.
Size of funding
Description of project
Gujarat Maritime Board has proposed port terminal, comprising of 300 m long berthing structure as a Wharf, constructing a solid pre-cast CC Block where with backup area to facilitate cargo handling at Rozi Pier site of Bedi Port. The proposed private investors will be JM Baxi (100 m Block Jetty) / Arcadia Shipping & Trading Co. (100 m Block Jetty) / Arvind & Co. Shipping Agency Pvt. Ltd., (50 m Block Jetty) and Ruchi Infrastructure (50 m Block Jetty). The proposed construction of waterfront is in alignment of the existing 400 m long piled and 100 m pre cast cc block wharf. The constructed wharf will be utilized for berthing of the smaller vessels and reclaimed area will be used for the godown / storage of cargo. The proposed wharf will enhance annual cargo handling capacity of the Rozi Pier terminal by 1 to 1.5 lakh Million MT / annum and total cargo handling capacity will be around 3 million MT /annum for this total 400 m wharf.
Date of commencement
- November 2007 - July 2008.
Due date
Publications/Outcomes/Reports/News clippings/Photos
Project Manager Name
- Nischal Joshi (Sr.Manager Project)
Designation & e-mail